Flood defence project on Isle of Cumbrae completed

Flood defence project on Isle of Cumbrae completed

Mill Burn

Works have been completed for a multi-million-pound Flood Protection Scheme on the Isle of Cumbrae, amid flooding risks from the Mill Burn.

Many homes and businesses within Millport have been at risk of flooding from the Mill Burn, particularly along Crawford Street, Cardiff Street and Golf Road. 

To cut this risk, in January North Ayrshire Council started work on the Millburn Flood Protection Scheme. 



The project will help improve the safety and security of the island’s residents against heightened coastal flooding dangers and localised flooding.

It includes a new 57-metre-long precast concrete sea wall built along West Bay Road from Cosy Corner at Millburn Street, as well as a 465m relief culvert, with a flow inlet chamber, at the top end of Golf Road to help lessen the volume of water coming through the existing Mill Burn at high flows.

Excess water will be discharged from the culvert through the new sea wall directly onto the shore at West Bay Road and away from residential properties.

On 19 October, the project was completed and was immediately tested during Storm Boelo the following weekend, with reports confirming that the system performed well in preventing flooding in the Mill Burn and on West Bay Road. 



Councillor Eleanor Collier, cabinet member for Green Environment and Economy, said: “We carried out a programme of public consultation, which included an online questionnaire and an exhibition of the plans at Garrison house, to ensure local residents, community groups and businesses were aware of the plan.

“It [the project] follows on from the successful £48million onshore and offshore Millport Flood Protection Scheme that was completed in 2024 to improve the safety and security of the island’s residents against increased coastal flooding threats.”

The works included:

  • A total of 37 precast concrete wall units measuring 3.1m high being placed along the coastal shoreline on West Bay Road
  • A 465m culvert made of 900mm diameter precast concrete pipes
  • Roughly 140 cubic metres of concrete for the precast sea wall units foundations, inlet chamber and new access ramp to the beach at West Bay Road
  • A 2.7m x 3.7m transition chamber
  • A total of 17 precast box culvert units measuring 2.7m by 1m

The main contractor for the project was McFadden (Civils) Ltd. A company spokesperson said: “We worked closely with North Ayrshire Council, the local community and other stakeholders to ensure successful completion of the project. It was a fantastic project to be a part of.”

The works were managed on behalf of the council by Turner & Townsend, with support being given from the principal designer Tetra Tech.

The Scottish Government contributed 80% towards the overall costs of the project, with the council meeting the remaining 20%.