M8 Woodside Viaducts reopening delayed again as costs climb to £185m

M8 Woodside Viaducts reopening delayed again as costs climb to £185m

Drivers on Glasgow’s M8 will wait longer for relief from the Woodside Viaduct roadworks, after the Scottish Government confirmed another delay to the emergency repairs.

The eastbound carriageway is now expected to reopen fully in early 2027, with westbound works due to finish in the second half of next year. That misses the autumn 2026 target set after earlier setbacks.

The latest slippage was confirmed in the Scottish Parliament on 17 November. Transport Secretary Stephen Flynn said: “Extensive and essential concrete repairs are required to joints. We anticipate that the eastbound carriageway will reopen in early 2027 and we expect the westbound works to be completed in the second half of next year.



“It is opportune that I update the Parliament that we expect the costs of the completed project to be in the region of £175 million to £185m.”

That is a significant increase on the £81m estimate reported in 2023.

Scottish Labour MSP Pauline McNeill expressed disappointment that another deadline had been missed and called for better communication with the public. She said: “I hope that the cabinet secretary shares my disappointment, because the road was supposed to be opened in autumn 2026 after five years of work.”

The current programme is only a stopgap. Transport Scotland said the steel supports, which will cost up to £185m, have a limited lifespan, will need ongoing maintenance and are unsuitable as a permanent solution.



The agency is developing a permanent solution and is weighing three options: repairing the existing viaducts, replacing them entirely or demolishing this section of the M8. The most expensive option could cost as much as £500m, according to estimates published during a public consultation earlier this year. Any of them raises the prospect of several more years of construction after the current restrictions are lifted.

The viaducts carry about 150,000 vehicles a day through the north of Glasgow city centre, linking Craighall and Charing Cross. Restrictions have been in place since 2021, when structural assessments found serious deterioration in the concrete supports beneath the elevated motorway.

The repair programme involves installing temporary steel supports at 23 locations, shifting the weight of the motorway away from deteriorating joints. Work has been complicated by underground infrastructure, including the Glasgow Subway tunnels and a sewer found in a different location from that shown in existing records.