Two primary schools in Airdrie undergo major upgrades
Corpus Christi PS investment announcement
Two primary schools in Airdrie are undergoing upgrades to their buildings, which form part of a £30 million investment programme.
At Corpus Christi Primary in Calderbank, the roof was replaced earlier in 2026.
For 2027, wall and window upgrades are scheduled, followed by heating and ventilation and a rewiring programme in a phased approach.
At Chapelside Primary, work is also underway and is also being delivered in phases.
In the summer of 2026, toilet upgrades were completed, and the school’s boilers have been replaced.
A contract has been given to replace the roof, with work beginning earlier in November. It is anticipated to take around 30 weeks.
All windows will then be replaced and a new external cladding system installed, with work anticipated to commence in summer next year. Part of that project will include ventilation improvements.
The school plans to redecorate, upgrade furniture and enhance the external areas and playground once the main work is completed.
Councillor Michael McBride, convener of education, children and Families, said: “We’re determined to improve the school estate and provide learning environments where pupils can realise their full potential.”
The work forms part of the council’s Targeted Investment Programme - which delivers improvements based on the condition of school buildings.
The two schools are among up to nine other schools in North Lanarkshire benefiting from a £30m targeted investment allocation.