Work to start for Grangemouth Sports Complex and Mariner Centre upgrade

Work to start for Grangemouth Sports Complex and Mariner Centre upgrade

Work will start in the New Year on a £1 million programme to enhance pool and changing facilities at Grangemouth Sports Complex and the Mariner Centre in Camelon.

The initial phase is anticipated to start at Grangemouth Sports Complex during January, and to go on for roughly eight weeks. While the work is being delivered, the swimming pool and changing village, including the sauna area, will be temporarily closed.

The planned improvements include: 



  • Full refurbishment of the changing village, sauna changing area and toilets
  • Essential maintenance works underneath the swimming pool
  • Refurbishment of foyer toilets
  • Fitness studio upgrade

Falkirk Council will work closely with customers, swimming clubs and lesson participants to reduce disruption where possible. 

Through the community swimming programme in local high schools and Mariner Centre, customers will still be able to access swimming, and as plans are finalised, additional information on swimming lessons, club arrangements and other available options will be disclosed.

Some of the maintenance work will go ahead underneath the pool and will not be visible once completed, but the refurbishment of the changing facilities will make a clear difference for customers.



After the completion of the Grangemouth project, similar works are provisionally planned to go ahead at the Mariner Centre between March and April.

Refurbishment of the changing village lockers, cubicles and toilets as well as the installation of new water features within the pool are among the works of the planned programme. 

Councillor Paul Garner, acting leader of Falkirk Council, said: This £1 million investment will improve facilities at two important leisure centres used by communities across the Falkirk area and extend their working lives.

“These improvements will create better, more modern facilities and help ensure both Grangemouth Sports Complex and the Mariner Centre continue to serve local communities in the years ahead.”

Throughout the project, customers will be kept up-to-date, with the confirmation of start dates, closure periods, reopening dates and alternative arrangements being included in updates as they become available. 

Looking ahead, through the council’s website and social media channels, more information will be shared.