Ardrossan Campus hit with further delays and £10m cost increase
The completion of the new state-of-the-art Ardrossan Community Campus has been delayed yet again and costs have risen by a further £10 million.
About this development:
- Authority:North Ayrshire
- Type:Education
- Applications:
- Team:jmarchitects (architect), Morgan Sindall (contractor), Wallace Whittle (mechanical & electrical engineer), Blyth+Blyth (civil & structural engineer), Carbon Futures (net zero consultant), Sandy Brown (acoustic consultant), Jensen Hughes (fire engineer), ECD Architects (Passivhaus consultant), Hirst (landscape architect), Faithful+Gould (project manager & cost consultant)
An update on the progress of the campus, set to be provided at a meeting of North Ayrshire Council’s Cabinet on Tuesday, confirmed that the new facility - which will incorporate an early years centre, primary and secondary school, library and swimming pool - will be completed at the end of May 2028 and open for its first intake of pupils a few months later in August.
The report also details that the additional removal work, and associated safety measures, increased the cost of the project by £9.97m, with the total cost now at £124.6m.
The council has confirmed the added costs will be covered through previously approved funding arrangements agreed in February 2026.
According to the report, the revised timescales for the campus are a result of recent works to remove contaminants which were encountered during early excavation works.
As works progressed on site, and in accordance with best practice, testing of excavated materials had continued in order to ensure all health and safety standards were maintained. Appropriate Safe Systems of Work were immediately implemented by the main contractor, with an independent review confirming these measures to be proportionate and compliant
Moving forward, the report also confirms that those contamination issues have now been addressed, and that the enhanced safety measures put in place are no longer required.
Construction has moved forward to steel frame erection, representing a major milestone in this important project.
Councillor Eleanor Collier, cabinet member for Green Environment and Economy, said: “While it is disappointing and frustrating that the opening of the Campus has had to be delayed, we have always been clear that health and safety must come first. The scale of what we are developing can’t be overstated. This was a huge, unkept piece of brownfield land that had been lying derelict and unused for decades.
“As a former industrial brownfield site we always knew that some risks would only be fully confirmed once deep excavation had been carried out. Despite that, the report also includes some encouraging news, with the project reaching a significant milestone on the construction process as steel work is now rapidly being erected on-site. We are looking forward to a steel signing event with local pupils in the coming months as we build excitement in the run-up to the opening.
“This Campus will change lives for the better, it will serve the community for years to come and be well worth the wait. We thank everyone for their patience and promise to provide further updates when we have them. In the meantime, we are now looking forward with real optimism to what promises to be a transformational development for Ardrossan and the wider community.”
The new campus is the first and key phase in the Ardrossan Coastal Quarter plans which will see the derelict site completely regenerated. As well as the state-of-the-art school campus the vision for the wider site also includes the provision of new housing and commercial uses.








